Saskatchewan Monthly Construction Update - September 2026

CANADA, September 30 - Released on September 30, 2026

Construction season in Saskatchewan continues at a steady pace as projects progress into the fall.

Infrastructure projects that have recently achieved substantial construction completion include a new Operations and Service Delivery Maintenance Shop in North Battleford, an elevator upgrade at the King's Bench Courthouse in Battleford and installation of new plumbing at the Walter Scott Building in Regina.

"The Government of Saskatchewan remains committed to informing residents of important construction and renovation projects across Saskatchewan as they continue to move forward," SaskBuilds and Procurement Minister Sean Wilson said. "On behalf of government, I would like to extend a thank you to the countless workers and partners across our province for their dedication and efforts to creating and improving vital infrastructure."

The September edition of the Saskatchewan Monthly Construction Update (MCU) features two infrastructure projects receiving essential upgrades:

  • Electrical upgrades at the Saskatchewan Polytechnic Moose Jaw Campus; and
  • Multi-year repairs of the L.F. McIntosh parkade in Prince Albert.

Saskatchewan Polytechnic Moose Jaw Campus Upgrades

The Saskatchewan Polytechnic Campus in Moose Jaw is undergoing upgrades to replace key electrical and mechanical infrastructure within the facility.

The project is a two-phased approach beginning with electrical work in phase one followed by mechanical upgrades in phase two.

Electrical infrastructure at the Moose Jaw Campus was originally installed in the 1950s with replacement parts now obsolete. Replacement of this key equipment will ensure it is easier to maintain and repair. This project was completed with minimal to no impact on students and faculty within the building.

"This investment strengthens the foundation that students, instructors and staff rely on every day," Wilson said. "By updating the school's electrical infrastructure, programs will not be negatively impacted by electrical disruptions, while providing a safe and reliable environment to support education in the province."

As part of the electrical infrastructure upgrades, the newly installed switchgear has the capability to provide remote monitoring. On-device thermal monitoring reduces the need for third party thermal image testing and requires minimal maintenance, helping maximize uptime.

A row of large electrical control cabinets inside a utility or industrial building. The cabinets are white with small screens, buttons, switches, and warning labels on the front. Each section contains controls for monitoring and switching electrical power. Bright yellow caution labels and red DANGER signs are attached throughout. Green Electric nameplates run along the bottom. The equipment is neatly arranged in a clean indoor space with an exposed ceiling above.  

Phase one of the project is anticipated to be completed in fall 2026, with phase two expected the following year.

Alliance Energy Ltd. has been contracted for phase one work. The general contractor for phase two has not been determined at this stage of the project.

L.F. McIntosh Building Parkade Repairs

The Government of Saskatchewan is investing in the long-term preservation of the L.F. McIntosh Building Parkade in downtown Prince Albert through a rehabilitation project that will strengthen the structure, improve durability and extend its service life. The work will help ensure the parkade continues to serve employees and visitors safely and effectively.

The post-tensioned concrete design creates a brighter and more efficient parking structure than conventional reinforced concrete parkades. Over time, however, exposure to water and environmental conditions can cause corrosion and deterioration.

This multi-year rehabilitation project addresses these challenges through targeted repairs and specialized protective measures. The project began in June 2020 with an initial engineering inspection. 

A large indoor construction area with a freshly coated, glossy floor stretching into the distance. The wet surface reflects the ceiling and surrounding structures like a mirror. Temporary blue safety netting lines the right side, while exposed concrete beams and utility pipes run overhead. A single worker stands far in the background using a long-handled tool on the floor. Buckets, power cords, a work light, and cardboard boxes are scattered around the foreground, indicating active floor-finishing or sealing work in a parking garage 

Work completed to date includes the repair, replacement and restoration of parkade elements such as damaged columns, beams and cables, as well as concrete delaminations and affected curbs. Teams have applied advanced waterproof coatings that seal parking decks and help prevent water, salt and other contaminants from reaching critical structural components.

"CCD Western Ltd. has been committed to partnering with SaskBuilds and Procurement's ongoing maintenance program of the L.F. McIntosh Parkade. CCD Western Ltd. has been charged with the post-tension cable repair and restoration over the past few decades," CCD Western Ltd. Project Manager David MacLeod said. "This long-term partnership has ensured that continuity in repair standards has been prioritized, adding value to maintaining the serviceability of this structure, doing our bit to keep Saskatchewan structures strong."

A freshly resurfaced parking garage level with a dark gray, textured floor extending toward the far end of the open structure. Bright yellow parking stall lines are painted across the surface, while a row of orange safety cones blocks off the newly finished area. Green protective tarps hang along the left side, and open wall sections on the right let in daylight. A folding barricade sign stands near the foreground. The floor appears newly coated, clean, and uniform, with a slightly reflective finish. 

Upcoming construction activities include the replacement of four reinforcement cables and approximately 1,250 m2 of damaged traffic deck surfaces. Concrete spot repairs will take place throughout the work area to prepare the surface before protective coatings are applied.

"We are really looking forward to this project and getting started on the traffic membrane installation," Excel Coatings Ltd. owner Gord Folk said. "This specialized coating is essential for long-term durability and structural protection and our team is ready to deliver a high-quality, long lasting traffic membrane that ensures protection for years to come."

The final phase of the project, which includes both reinforcement cable and surface repairs, will begin in fall 2026. Completion of the current phase is anticipated in winter 2026-27.

Did You Know: 

  • The new equipment installed during electrical upgrades at the Saskatchewan Polytechnic Moose Jaw Campus has the smallest footprint currently available.
  • Each level of the L.F. McIntosh Building Parkade is approximately the size of four standard basketball courts (1,700 m2). There are seven levels in total, with a total parking stall count of 294 stalls, making it one of the few mid-sized parkades in Saskatchewan.

The 2026-27 Provincial Budget delivers a capital budget in Saskatchewan of $4.3 billion, one of the largest total capital budgets in Saskatchewan's history.

-30-

For more information, contact:

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Share this page:

Advanced Search Options

Search for:

Search scope:

Type:

Search in:

Date range:

The last

Sort by:

Sign up for:

Canadian Real Estate Today

The daily local news briefing you can trust. Every day. Subscribe now.

By signing up, you agree to our Terms & Conditions.